Eridge Mk2 is slowly getting ever closer to where Mk1 finished, so we can move on from topic on the baseboards viewtopic.php?f=25&t=36 . Scenic landforms now cover the London end, showing the increased depth of scenery in the new version. These show how the low embankment of made ground on which the whole station rests (real) transition into a cutting as the topography rises (fictitious).

P5310011.JPG
P5310011.JPG (66.9 KiB) Viewed 7698 times


P5310027.JPG
P5310027.JPG (94.84 KiB) Viewed 7698 times


More on the odd looking locomotive later!

At the station end, the stream course has been carved out from extensions to the polystyrene baseboard surface, and the platforms have been reshaped but not yet bedded into the spaces between the ballast. Some new detail work has also been done on the main station building but things still look a bit precarious for any prospective traveller!

P5310016.JPG
P5310016.JPG (88.47 KiB) Viewed 7698 times


P5310028.JPG
P5310028.JPG (114.14 KiB) Viewed 7698 times


P5310026.JPG
P5310026.JPG (114.7 KiB) Viewed 7698 times


P5310018.JPG
P5310018.JPG (91.33 KiB) Viewed 7698 times


P5310021.JPG
P5310021.JPG (78.25 KiB) Viewed 7698 times


P5310038.JPG
P5310038.JPG (59.21 KiB) Viewed 7698 times


P5310043.JPG
P5310043.JPG (81.31 KiB) Viewed 7698 times


P5310044.JPG
P5310044.JPG (101.4 KiB) Viewed 7698 times


And what about that locomotive? Not one that would be permitted on the line in reality, and it raised some eyebrows amongst the diehard Southerners, but it's a Churchward 28xx from a Finney kit - Mike bought it at the MRJ show (!) when it was one of the first etched kits for a 'large' engine. The chassis has been around for some years, but it now has a body and tender. With a Portescap motor, inside working valve gear, and pickups in the tender only, like all of Mike's locomotives it performed very nicely indeed.

P5310034.JPG
P5310034.JPG (120.62 KiB) Viewed 7698 times


P5310035.JPG
P5310035.JPG (108.51 KiB) Viewed 7698 times


Rumours abounded that more of the boards were about to be upturned for completion of wiring, so things are certainly progressing.
Rod

User avatar
Rod Cameron
Posts: 637
Joined: Fri Jul 25, 2008 12:01 pm

Re: Eridge rebuild

Postby Rod Cameron » Sun Jun 03, 2012 11:44 am

Normally 'before and after' pics usually show more advanced development in the 'after' shots - we seem to be doing it the other way round! Don't worry, it will catch up eventually ...

051023 062.JPG
051023 062.JPG (92.6 KiB) Viewed 7614 times


P5310011.JPG
P5310011.JPG (66.9 KiB) Viewed 7614 times


0302b_brighton9_ss.jpg
0302b_brighton9_ss.jpg (91.7 KiB) Viewed 7614 times


P5310017.JPG
P5310017.JPG (106.09 KiB) Viewed 7614 times
Rod

User avatar
Mark Tatlow
Posts: 695
Joined: Tue Dec 02, 2008 11:24 pm

Re: Eridge rebuild

Postby Mark Tatlow » Sun Jun 03, 2012 8:13 pm

It does look impressive with the wide baseboards; definitely food for thought......
Mark Tatlow

Terry Bendall
Posts: 1609
Joined: Sun Jul 27, 2008 7:46 am

Re: Eridge rebuild

Postby Terry Bendall » Mon Jun 04, 2012 4:31 pm

Looking very nice Rod. The platform canopy is very impressive - as is everything else. A good job Scaleforum is moving to a larger venue!


Terry Bendall

User avatar
Re6/6
Posts: 405
Joined: Sat Jul 26, 2008 4:53 pm

Re: Eridge rebuild

Postby Re6/6 » Tue Jun 05, 2012 9:12 am

It certainly has the feel of the real thing!
John

User avatar
Mike Garwood
Posts: 503
Joined: Sun Aug 03, 2008 4:51 pm

Re: Eridge rebuild

Postby Mike Garwood » Tue Jun 05, 2012 9:24 am

Looking really good. It'll be great to see it in the flesh...crack on fellas, very inspiring.

Mike

User avatar
Tim V
Posts: 2214
Joined: Tue Jul 29, 2008 4:40 pm

Re: Eridge rebuild

Postby Tim V » Tue Jun 05, 2012 10:00 am

Extra depth of layout = a Good thing.
Tim V

User avatar
Rod Cameron
Posts: 637
Joined: Fri Jul 25, 2008 12:01 pm

Re: Eridge rebuild

Postby Rod Cameron » Sat Oct 06, 2012 2:01 pm

Some photos of the new brass canopy structures to replace the former wood, plasticard (did we ever do straw as well?) versions which kept getting blown down by some wolf or other (shurely shome mistake? - Ed.).

IMG00337-20121004-2029.jpg
IMG00337-20121004-2029.jpg (107.46 KiB) Viewed 7128 times


IMG00339-20121004-2030.jpg
IMG00339-20121004-2030.jpg (93.72 KiB) Viewed 7128 times


IMG00345-20121004-2033.jpg
IMG00345-20121004-2033.jpg (88.45 KiB) Viewed 7128 times


IMG00349-20121004-2105.jpg
IMG00349-20121004-2105.jpg (117.18 KiB) Viewed 7128 times
Rod

User avatar
Tim V
Posts: 2214
Joined: Tue Jul 29, 2008 4:40 pm

Re: Eridge rebuild

Postby Tim V » Sat Oct 06, 2012 7:33 pm

Bit of a lack of foundations there Rod....
Tim V

User avatar
Rod Cameron
Posts: 637
Joined: Fri Jul 25, 2008 12:01 pm

Re: Eridge rebuild

Postby Rod Cameron » Sun Oct 07, 2012 12:43 pm

But at least (if you look at the similar photo in an earlier post) there's now a door!

Seriously though Tim, they're still working on the dimensional relationships between the road, station building and footbridge before finalising the underside.
Rod

DougN
Posts: 874
Joined: Wed Sep 01, 2010 9:57 am

Re: Eridge rebuild

Postby DougN » Mon Oct 08, 2012 1:07 am

Nice door.... but as Bugs Bunny once said " I never studied the law of gravity" :twisted:
Doug
Still not doing enough modelling

User avatar
Rhobat Bryn
Posts: 48
Joined: Tue Oct 02, 2012 4:05 pm

Re: Eridge rebuild

Postby Rhobat Bryn » Mon Oct 08, 2012 12:19 pm

Just how big is this layout exactly?
Nant Hendre - Rheilffordd Y Barri

User avatar
Rod Cameron
Posts: 637
Joined: Fri Jul 25, 2008 12:01 pm

Re: Eridge rebuild

Postby Rod Cameron » Tue Oct 09, 2012 4:20 pm

Rhobat Bryn wrote:Just how big is this layout exactly?


About 25ft visible length plus fiddle yards each end.
Rod

User avatar
Rhobat Bryn
Posts: 48
Joined: Tue Oct 02, 2012 4:05 pm

Re: Eridge rebuild

Postby Rhobat Bryn » Tue Oct 09, 2012 6:51 pm

Rod Cameron wrote:
About 25ft visible length plus fiddle yards each end.


Many thanks.

Looks terrific by the way, I particularly like the shape of the landscape for the cutting by the bridge.
Nant Hendre - Rheilffordd Y Barri

User avatar
Rod Cameron
Posts: 637
Joined: Fri Jul 25, 2008 12:01 pm

Re: Eridge rebuild

Postby Rod Cameron » Wed Mar 12, 2014 1:52 pm

I hope Mark won't mind me posting these, but here is some of his amazing CAD and (Shapeways) 3D printing work for the first part of the station footbridge.

No more words needed.

Eridge%20Station%20Footbridge%201[3].jpg
Eridge%20Station%20Footbridge%201[3].jpg (46.27 KiB) Viewed 5502 times


Eridge%20Station%20Footbridge[1].jpg
Eridge%20Station%20Footbridge[1].jpg (29.97 KiB) Viewed 5502 times


2014-02-10%2015.48.02[2].jpg
2014-02-10%2015.48.02[2].jpg (47.53 KiB) Viewed 5502 times


2014-02-10%2015.48.24[5].jpg
2014-02-10%2015.48.24[5].jpg (47.06 KiB) Viewed 5502 times


2014-02-10%2015.48.56[2].jpg
2014-02-10%2015.48.56[2].jpg (47.2 KiB) Viewed 5502 times
Rod

User avatar
jim s-w
Posts: 1696
Joined: Wed Jul 30, 2008 5:56 pm

Re: Eridge rebuild

Postby jim s-w » Wed Mar 12, 2014 2:12 pm

That's going to be awkward to paint isn't it? :?

User avatar
Colin Parks
Posts: 597
Joined: Sun Oct 27, 2013 4:44 pm

Re: Eridge rebuild

Postby Colin Parks » Wed Mar 12, 2014 7:06 pm

Wow, super stuff!

Eridge Mk. 2 looks very nice indeed. I can't get over the fact that the visible area is only 25'. It looks to be much more. (I would have guessed 35') Given the painstaking work being done on every aspect of the layout's construction, how long before it will be exhibited?

All the best,

Colin

User avatar
Rod Cameron
Posts: 637
Joined: Fri Jul 25, 2008 12:01 pm

Re: Eridge rebuild

Postby Rod Cameron » Thu Mar 13, 2014 11:40 am

jim s-w wrote:That's going to be awkward to paint isn't it? :?


Hi Jim

Mark is having some problems logging on at the moment, but he says:

The construction was such that structural integrity was paramount and the design has proved to be very strong considering the thickness of material to print this although it is largely down to the “one-piece” construction method.

The intention is to spray main staircase structure (green) and then brush painted the foot steps (dark wood) afterwards , the open lattice “false work” structure hopefully aiding the latter.

The lattice “false work” is there only to glue the close board panelling too (Slaters plastikard 2mm ) and when complete will be totally hidden. If my maths are right then this will mean that internally the wood panelling will sit onto the step side kickboards leaving a lip and underneath the handrail which should in turn create a clean paint finish to the internal surfaces where the colour changes.

Equally the roof was omitted from the final design to ensure the roof trusses could be painted to the same standard.

Externally the close board panelling will butt tight to the handrail and finish below the level of the side structure so enclosing that surface.

Unfortunately i couldn’t animate that on CAD so there is a bit of fingers crossed in the above :)
Rod

User avatar
Rod Cameron
Posts: 637
Joined: Fri Jul 25, 2008 12:01 pm

Re: Eridge rebuild

Postby Rod Cameron » Thu Mar 13, 2014 11:51 am

Colin Parks wrote:Wow, super stuff!

Eridge Mk. 2 looks very nice indeed. I can't get over the fact that the visible area is only 25'. It looks to be much more. (I would have guessed 35') Given the painstaking work being done on every aspect of the layout's construction, how long before it will be exhibited?

All the best,

Colin


Hi Colin, and thanks!

It's possible it might be out on the road in around 18 months but possibly not in fully completed condition (we seem to make a habit of this!).

Unfortunately we have just had to vacate our permanent premises of 16 years and it's currently in store in Richard's garage. Fortunately however the boards, track and electrics are complete and it is now in the scenics and detailing phase so it can still be worked on. We have some options for new premises so hopefully it can be set up again soon.