Five turnouts, a diamond and a single slip, enough to get the up and down Consett main lines laid. My thanks to Stephen Freeman of Borg Rail for these.
-
- Web Team
- Posts: 1092
- Joined: Fri Mar 16, 2012 7:03 pm
Re: South Pelaw Junction
First lot of track and droppers have been fitted on boards 1 & 2 so I can now run a train over 12 foot of track making it 3 times longer than any other track work I've ever had. Turnout is wired but the operating mechanism is not fitted yet.
With a bit of luck, I'll be able to run a train over the full length of the layout by the weekend...
With a bit of luck, I'll be able to run a train over the full length of the layout by the weekend...
-
- Posts: 36
- Joined: Thu Mar 17, 2016 7:57 pm
Re: South Pelaw Junction
You'll soon be needing a 9F...…
Nice to see progress John.
Pete
Nice to see progress John.
Pete
-
- Web Team
- Posts: 1092
- Joined: Fri Mar 16, 2012 7:03 pm
Re: South Pelaw Junction
pete55 wrote:You'll soon be needing a 9F...…
Cheers Pete, you fancy building a Bradwell chassis for me
-
- Posts: 36
- Joined: Thu Mar 17, 2016 7:57 pm
Re: South Pelaw Junction
Seriously, try a re wheeled Bachmann.....you might be surprised!
-
- Web Team
- Posts: 1092
- Joined: Fri Mar 16, 2012 7:03 pm
Re: South Pelaw Junction
pete55 wrote:Seriously, try a re wheeled Bachmann.....you might be surprised!
Well, I've already got the wheels so no harm in trying I guess...
-
- Web Team
- Posts: 1092
- Joined: Fri Mar 16, 2012 7:03 pm
Re: South Pelaw Junction
Progress, the down Consett is now completely laid and wired.
-
- Web Team
- Posts: 1092
- Joined: Fri Mar 16, 2012 7:03 pm
Re: South Pelaw Junction
So, over the last couple of days, for various reasons I've made the decision to scrap the existing track (it will eventually find a use in the fiddle yard so it won't be completely wasted) but I figured before I do that, I'd better have a go at building some turnouts and the single slip. I've built turnouts before but always from kits so I've never had to build a crossing v for example.
Here's the result of a couple of hours work tonight, I love the flow that the track work has when built as a single unit...
Lots still to do and some of the vees need a bit more work but, even just taped down, I can run wagons through the crossings.
Here's the result of a couple of hours work tonight, I love the flow that the track work has when built as a single unit...
Lots still to do and some of the vees need a bit more work but, even just taped down, I can run wagons through the crossings.
-
- Posts: 645
- Joined: Tue Nov 11, 2008 6:51 pm
Re: South Pelaw Junction
John Donnelly wrote:So, over the last couple of days, for various reasons I've made the decision to scrap the existing track (it will eventually find a use in the fiddle yard so it won't be completely wasted)
Sorry to hear that, did you have problems?
Steve Carter
-
- Posts: 1600
- Joined: Wed Feb 11, 2015 3:39 pm
Re: South Pelaw Junction
John Donnelly wrote:S.... I love the flow that the track work has when built as a single unit...
Looks great to me ... will be fun watching this develop.
Tim Lee
-
- Web Team
- Posts: 1092
- Joined: Fri Mar 16, 2012 7:03 pm
Re: South Pelaw Junction
Trackwork is progressing:
John
John
-
- Web Team
- Posts: 1092
- Joined: Fri Mar 16, 2012 7:03 pm
Re: South Pelaw Junction
No progress on the layout as such as I'm waiting on some things from Tim Horn but I've not been idle and I've ventured in to two areas I've previously had no experience with, semaphore signalling and electronics.
First up is an LNER tubular post signal from the MSE kit, by far the fiddliest thing I've ever soldered but after much swearing and burnt fingers it is complete apart from the rear of the signal arm which I'll do after painting. I've made a couple of mistakes along the way but, despite that, it works as intended:
https://youtu.be/eZTfIqAWs8g
For the electronics, I'm starting with turnout operation and I've decided on a Cobalt Lever Frame, MERG, servo combination so I've made up a MERG SERVO4 board, programmed a servo and connected the lever:
https://youtu.be/y-kAotgsafQ
First up is an LNER tubular post signal from the MSE kit, by far the fiddliest thing I've ever soldered but after much swearing and burnt fingers it is complete apart from the rear of the signal arm which I'll do after painting. I've made a couple of mistakes along the way but, despite that, it works as intended:
https://youtu.be/eZTfIqAWs8g
For the electronics, I'm starting with turnout operation and I've decided on a Cobalt Lever Frame, MERG, servo combination so I've made up a MERG SERVO4 board, programmed a servo and connected the lever:
https://youtu.be/y-kAotgsafQ
-
- Forum Team
- Posts: 3923
- Joined: Sun Jun 29, 2008 8:02 pm
Re: South Pelaw Junction
The signal looks good. MSE do a nice mount for servo operation of signals so they can also work from the Servo4.
-
- Web Team
- Posts: 1092
- Joined: Fri Mar 16, 2012 7:03 pm
Re: South Pelaw Junction
grovenor-2685 wrote:The signal looks good. MSE do a nice mount for servo operation of signals so they can also work from the Servo4.
Thanks Keith, I didn't know about the mount so that's good to know.
-
- Web Team
- Posts: 1092
- Joined: Fri Mar 16, 2012 7:03 pm
Re: South Pelaw Junction
Plywood from Tim Horn (superb service) with the track plan etched in to it:
Three quarters of the layout:
John
Three quarters of the layout:
John
-
- Posts: 825
- Joined: Fri Jul 15, 2011 11:09 pm
Re: South Pelaw Junction
Brilliant way of sidestepping the potential for grief when aligning and fixing paper templates! Did you arrange for any part of the plan to be mirror-etched on the underside of the board, e.g. to assist location of droppers or other connections that needed to be made through the deck?
-
- Web Team
- Posts: 1092
- Joined: Fri Mar 16, 2012 7:03 pm
Re: South Pelaw Junction
John Palmer wrote:Brilliant way of sidestepping the potential for grief when aligning and fixing paper templates!
One of the reasons why I did it this way, I also had visions of the glue holding the paper down failing over time and the track lifting.
John Palmer wrote:Did you arrange for any part of the plan to be mirror-etched on the underside of the board, e.g. to assist location of droppers or other connections that needed to be made through the deck?
No, but I'm hoping to surface mount everything including the servos for ease of access.
John
-
- Posts: 2527
- Joined: Sun Jul 20, 2008 3:54 pm
Re: South Pelaw Junction
I'm not a great fan of the "Like Button" but If I'd had one I'd've used it.
-
- Web Team
- Posts: 1092
- Joined: Fri Mar 16, 2012 7:03 pm
Re: South Pelaw Junction
All sleepers are down and I've finally got some track, all 4' of it, laid with droppers fitted:
I think I may have some gauging issues though...
I think I may have some gauging issues though...
-
- Posts: 36
- Joined: Thu Mar 17, 2016 7:57 pm
Re: South Pelaw Junction
NYMR meets S Pelaw!!
Was Rich driving the rat?!
Pete
Was Rich driving the rat?!
Pete
-
- Web Team
- Posts: 1092
- Joined: Fri Mar 16, 2012 7:03 pm
Re: South Pelaw Junction
Party due to the current health crisis, SPJ (two thirds of it anyway) has a new, temporary, home, my rather unfinished living room. It's a bit of a surprise to see how big even two boards are in a normal environment rather than a 160' long room.
No excuses for not cracking on with it and it gives me an excuse for not finishing the house as it is in the way
No excuses for not cracking on with it and it gives me an excuse for not finishing the house as it is in the way
-
- Posts: 95
- Joined: Sun Dec 17, 2017 8:49 pm
Re: South Pelaw Junction
Lovely trestles, who's make are they?
-
- Web Team
- Posts: 1092
- Joined: Fri Mar 16, 2012 7:03 pm
Re: South Pelaw Junction
RAO wrote:Lovely trestles, who's make are they?
Screwfix
-
- Posts: 643
- Joined: Tue Oct 02, 2012 3:31 pm
Re: South Pelaw Junction
It beats looking at the television. LOL. I can't see my wife agreeing to allow me to do this in our front room.
Keep Safe
Dave
Keep Safe
Dave
-
- Web Team
- Posts: 1092
- Joined: Fri Mar 16, 2012 7:03 pm
Re: South Pelaw Junction
Serjt-Dave wrote:It beats looking at the television. LOL. I can't see my wife agreeing to allow me to do this in our front room.
As a widower, there is no domestic authority to object...
Return to “Layouts and Operations”
Who is online
Users browsing this forum: No registered users and 4 guests